Maintenance

Fire Power

In order to produce high-quality electricity, specialized technical personnel in the electrical and mechanical fields are stationed at the power plant, and they provide an optimal operating environment according to changes in operating conditions such as vibration, temperature, and pressure of the steam turbine, generator, boiler, and its components, the rotating body.

  • Facilities Sector
    • Main control and auxiliary control equipment
      (DCS,PLC and computer equipment etc.)
    • Field instrument / measuring instrument
    • Test drive and technical diagnosis
  • Possible Areas
    • Design, manufacture and maintenance of related facilities(BLT, TBN, BNR, DAS, VMS, SCDA etc.)
    • Electronic control card manufacturing, repair, and precision inspection
    • Control system commissioning and precision inspection
    • Various instrumentation works
NO Project Name Orderer Performance Period
102 Unit 6 Measurement and Control Equipment Disassembly Inspection Works KEPCO KPS 2025.03~2025.04
101 2025 Samcheok Unit 2 Measurement and Control Equipment Planned Preventive Maintenance Works (Class B) Korea Southern Power 2025.03~2025.06
100 Samcheok Measurement Control Facility Recurring Maintenance Service Korea Southern Power 2015.07~2025.06
99 2024 Samcheok Unit 1 Measurement and Control Equipment Planned Preventive Maintenance Works (Class A) Korea Southern Power 2024.04~2024.07
98 2023 Samcheok Unit 2 Measurement and Control Equipment Planned Preventive Maintenance Works Korea Southern Power 2023.04~2023.07
97 Samcheok Unit 2 Turbine Area Measurement and Control Equipment Disassembly Inspection Works KEPCO KPS 2021.04~2021.06
96 Samcheok Unit 2 Measurement and Control Equipment Long-Term Simple Maintenance Korea Southern Power 2021.04~2021.06
95 2022 Samcheok Unit 1 Measurement and Control Equipment Planned Preventive Maintenance Works Korea Southern Power 2022.03~2022.05
94 2020 Samcheok Unit 1 Measurement and Control Equipment Planned Preventive Maintenance Works (Class B) Korea Southern Power 2020.09~2020.12
93 2020 Samcheok Unit 2 Measurement and Control Equipment Planned Preventive Maintenance Works (Class B) Korea Southern Power 2020.03~2020.05
92 2018 Samcheok Unit 2 Measurement and Control Equipment Planned Preventive Maintenance Works (Class A) Korea Southern Power 2018.04~2018.07
91 2017 Samcheok Unit 1 Measurement and Control Equipment Planned Preventive Maintenance Works (Class A) Korea Southern Power 2017.10~2018.01
90 Boryeong Thermal Power Plant Unit 6 Measurement and Control Equipment Disassembly Inspection Works KEPCO KPS 2017.10~2017.11
89 Boryeong Thermal Power Plant Units 4 and 7 Measurement and Control Equipment Disassembly Inspection Works KEPCO KPS 2017.05~2017.06
88 2016 Cheongna Energy Heat Supply Facility Routine Maintenance Works (Control Part) Geumhwa PSC 2016.09~2017.09
87 2016 Yeongheung Thermal Power Plant Unit 1 Measurement and Control Equipment Planned Preventive Maintenance Works Korea Southeast Power 2016.05~2016.06
86 2016 Planned Preventive Maintenance Works for Unit 7 (Measurement and Control Equipment) (Class B) Korea Southern Power 2016.03~2016.04
85 2016 Yeongheung Thermal Power Plant Unit 4 Measurement and Control Equipment Planned Preventive Maintenance Works Korea Namdong Power 2016.01~2016.03
84 Cheongna Energy Heat Supply Facility Routine Maintenance Works (Control Part) Geumhwa PSC 2015.09~2016.09
83 Yeongdong Thermal Power Plant Unit 2 Measurement and Control Equipment Planned Preventive Maintenance Works Korea Namdong Power 2015.10~2015.11
82 Yeongheung Thermal Power Plant Unit 3 Measurement and Control Equipment Planned Preventive Maintenance Works Korea Namdong Power 2015.10~2015.11
81 Yeongheung Thermal Power Plant Unit 2 Measurement and Control Equipment Planned Preventive Maintenance Works Korea Namdong Power 2015.05~2015.07
80 2015 Hadong Thermal Power Plant Unit 8 Measurement and Control Equipment Planned Preventive Maintenance Korea Southern Power 2015.05~2015.06
79 2015 Simple Maintenance Works for Unit 4 (Measurement and Control Equipment) Korea Namdong Power 2015.04~2015.04
78 Sancheong Green Power Units 1 and 2 Measurement and Control Equipment Routine Maintenance Service Korea Southern Power 2015.07~2018.06
77 Yeongheung Thermal Power Plant 2015 Simple Maintenance Works for Unit 1 (Measurement and Control Equipment) Korea Namdong Power 2015.03~2015.03
76 2015 Hadong Thermal Power Plant Unit 5 Measurement and Control Equipment Planned Preventive Maintenance Works (Class B) Korea Southern Power 2015.02~2015.03
75 Seoincheon Power Generation Headquarters Cheongna Energy Heat Supply Facility Routine Maintenance Works (2nd) Geumhwa PSC 2014.09~2015.09
74 Hadong Thermal Power Plant 2014 Planned Preventive Maintenance Works for Unit 6 (Class A) Korea Southern Power 2014.09~2014.10
73 Yeongheung Thermal Power Plant Unit 1 Measurement and Control Equipment Simple Maintenance Works Korea Namdong Power 2014.05~2014.06